Our current Wind Farm Projects
* Tallentire Wind Farm Nr Cockermouth, Cumbria for Renewable Energy Systems (RES). The Civil and Ancillary Works contract for the 6 turbine site commenced on 2nd July 2012 and included 7.5km of site roads, crane hardstandings & reinforced concrete foundations for the 6 nr 2MW Vestas wind turbines, control building, HV MV & Scada cabling and various off site highway improvement works. The site began generating in March 2013 and was commissioned in June 2013.See link below to the scheme Project Profile. * Roos Wind Farm Nr Hull, East Yorkshire for Renewable Energy Systems (RES). Civil and Ancillary Works for the 9 nr 2MW turbine site commenced on 9th January 2012 requiring construction of 4.5km of site roads, 9 crane hardstandings and turbine bases and a control building. Part of the site is founded on up to 18m of very soft marine alluvium which necessitated extensive ground improvement for site roads, crane hardstandings and deep CFA piling to support 5 of the turbine bases. The site was commissioned in March 2013. See link below to the scheme Project Profile. See also link to RES October 2012 Construction Newsletter (Click to view) * Wadlow Wind Farm, West Wratting, Cambridgeshire for Renewable Energy Systems (RES). The Civil and Infrastructure Works for the 13 turbine site commenced on 7th June 2011 and includes 8km of site roads, crane pads and reinforced concrete foundations for the 13 nr 2MW wind turbines. The site was fully commissioned and began generating in September 2012. See the link below for the scheme Project Profile.Visit the Forkers Ltd website for more information on Our current Wind Farm Projects