A453 – S11 Thrumpton Overbridge Reinforcement Survey, Nottingham
29-04-2015
Client:
Laing O’Rourke Construction North Ltd
Scope of work:
LDM scanned the inner face of each parapet down to the deck and the top surface of the parapet to both sides of the structure to establish rebar diameter, cover and spacing using the Hilti PS1000X-scan and PS200 Ferroscan.
The scanning allowed the project team to mark out the reinforcement prior to drilling the fixings for the new post positions avoiding hitting any reinforcement.Visit the LDM Scanning LTD website for more information on A453 – S11 Thrumpton Overbridge Reinforcement Survey, Nottingham